BusinessFEATUREDNews

EEP Earns $25mln from Power Supply to Data Miners

ADDIS ABABA – Ethiopian Electric Power (EEP) announced that it has made 25 million US dollars earnings last year from electricity supply to data mining companies operating in the country.

Bitcoin miners entered Ethiopia looking for low power costs after the government authorized data mining in 2022. This has created an additional source of foreign currency earnings for the state-owned enterprise EEP that also earned $140 million from export last year.

Ethiopia’s Power generating company entered power supply agreements with 24 licensed data mining companies last year, allowing EEP to collect electricity bills from local customers in forex for the first time.

Nine of these data mining companies became operational in the 2023/24 fiscal year that ended in June. On Wednesday, EEP’s Marketing bureau head Menelik Getahun said these active data mining companies have been paying their bills in forex.

The power producer’s initial annual plan was to provide the data miners with 882.48 million Gigawatts-hour (GWh) electricity, aiming to secure $27.71 million in revenue.

The annual forex earnings fell short of the company’s plan, however. Menelik said EEP supplied 796.28 million GWh to the data mining companies that paid $25 million in electricity bills.

The revenue was 90 percent of the revenue EEP’s officials had been hoping to collect. The electric power supply was not enough to meet data miners’ demands, said its marketing chief, explaining the cause of the revenue shortfall.

EEP, which generates 96% of the national electricity output from hydropower, currently operates 22 interconnected generation plants.

Last year, 84% of the output went to the local market and 9% to export amid a 16% increase in overall energy consumption.

its officials pin high hopes on the Grand Ethiopian Renaissance Dam (GERD) to fill in the nation’s power deficit and boost the economy. The Dam, currently 98 percent complete, has more than doubled its installed generating capacity to 550 MW after two more turbines started operations last week.